We put a new floor in Morag's house Me and Mike, I mean. Mike was the skilled labor, and I was the labor. Morag
already had hardwood floors, but they were so damaged from termites, water,
and age that there was no point in refinishing them. So we just laid down new
wood over the old floors. It took
about five days to do 850 square feet. But that includes losing most of the
first day trying to get the nailer to work. Once we finished that we were off
to the races. We put down Australian cypress. Looks great. Now we will see how
it holds up.